Hot water & TMV upgrade across a live 90-bed facility
A full central hot water and thermostatic mixing valve replacement on a live aged-care site — delivered with zero downtime for residents.
Client
Adelaide aged-care provider
Location
Western Adelaide, SA
Completed
2024
Scope of work
Commercial hot water
TMV replacement & certification
Out-of-hours staging
Compliance reporting
By the numbers
What the job delivered
0
Hours of resident downtime
90
Beds kept in continuous supply
3
Night shifts, start to finish
100%
TMV compliance restored
The challenge
A failing central hot water plant put reliable supply and TMV compliance at risk across a live aged-care facility that simply could not lose hot water. Vulnerable residents meant temperature safety and continuity were non-negotiable, and there was no scope to shut a wing down.
What we did
We planned and staged a full hot water and thermostatic mixing valve replacement out of hours, wing by wing, keeping every occupied area supplied throughout. Temporary connections maintained flow while new plant was commissioned, tested and certified against AS/NZS standards.
Site audit and staged works program agreed with facility management
Temporary hot water connections to keep every wing supplied
New plant and TMVs installed and commissioned over three night shifts
Full temperature testing, certification and digital compliance records handed over
On site
The outcome
The facility moved onto a reliable, fully compliant hot water system without a single interruption to residents — and now runs a scheduled TMV testing program with us to stay ahead of compliance.
“They worked around our residents, not the other way around. Every wing kept hot water the whole time and the compliance paperwork was spotless.”